St Mary’s Harbour Improvement Project Weekly Update- 30 October 2015

Here’s the latest from Kier Construction

Quay Extension:

Final mass concrete tie in complete.

Transfer of additional aggregates and cement on-going from the mainland.

Reinforcement and formwork for sea wall ongoing.

Grouting of the anchors on-going.

Fenders now island side.

Quay Widening:

10no level one pre-cast concrete units placed and anchored.

Foundation works 50% complete.

Works continue to foundations and pre-cast concrete units.

Oil interceptor, package pump station blower & pump station on site.

Harbourside building:

Ticket Office – Duchy works to fire alarm and intercom ongoing.

Freight Offices – Duchy works to install chiller works & electrical feed ongoing.

Freight Store – Wall and roof cladding on-going.

Balcony – Balustrades –installation 95% complete, roof membrane currently being placed, decking to follow.

Chiller – cold room doors ongoing and mains feed to chiller required for testing and commissioning.

Parting Carn:

Batching concrete for quay extension and widening foundations continues.

Demobilisation being undertaken.

Porthloo:

Bag filling operations for delivery to Parting Carn or direct to the quay now escalated to include weekends.

The second phase programme forms part of the above increased works.

Kier has installed cameras on all working vehicles with a recording facility for appraisals and record

purposes.