St Mary’s Harbour Improvement Project Weekly Update Week Ending 16 October 2015

Quay Extension

· Shuttering has been prepared for final 2 layers.

· Additional aggregate and cement being transferred from the mainland.

· Fendering transfer to St Mary’s expected next week.

Quay Widening

· Package Pump Station – complete and due for delivery to site next week.

· Solidification plant works on-going and due to be complete towards the end of this week.

· 4 pre cast wall units remaining, and to be brought over from Falmouth next week.

Harbourside building

· Ticket & Freight Offices –ready for Offering to the Client for take over.

· Freight Store – wall cladding commenced, roof to follow.

· Balcony – all plywood decking and firrings installed with balustrades to follow next week.

· Chiller – Roofing membrane to be installed. Awaiting delivery of cold room doors and mains feed to chiller.

Parting Carn

· Batching concrete for quay extension and widening foundations.

· Prefabrication of quay widening foundation reinforcement cages.

Porthloo

· Bag filling operations for delivery to Parting Carn or direct to the quay now escalated to include weekends.

· The second phase or final removal programme forms part of the above increased works.