St Mary’s Harbour Works Update From Kier- October 1st

Quay Extension:

Concreting to continue throughout the rest of the week to complete tie-in pours and concrete infill to berthing line.

All fendering now delivered to Falmouth, transfer to IOS on-going.

Quay Widening:

Package Pump Station – complete and being vested with the supplier.

Solidification plant expected from Falmouth this week, with works set to commence 1 October and last 10-14 days.

13no pre cast wall units remain to be brought over from Falmouth.

Harbourside building:

Ticket Office – handover by the end of this week.

Freight Store – 5 of 6 new columns installed, 6th to follow by the end of this week.

Freight Office – final 2nd fix carpentry.

Balcony – Steelwork installation has commenced and is due to be completed by the end of the weekend.

Chiller – Roofing membrane to be installed. Cold store ducting and doors in progress followed by commissioning.

Parting Carn:

Batching concrete for quay extension and freight store foundations.

Receipt of Quay Widening blocks.


Bag filling for delivery to Parting Carn or direct to the quay continues.

The second phase or final removal remains on target weather permitting for mid October 2015.