St Mary’s Harbour Improvement Project Weekly Update

Week Ending 25 September 2015

Quay Extension:

First of 5 concrete pours completed for the quay tie-in

Concreting to continue throughout the rest of the week

Crane & Jack up barge demobilised and left

All fendering now delivered to Falmouth

Quay Widening:

Package Pump Station – due to be delivered to Falmouth this week

Mobilising solidification plant to Falmouth this week, with works set to commence 28-30 Sep 15 and last 10-14

days.

13no pre cast wall units remain to be brought over

Harbourside building:

Ticket Office – Vinyl flooring to be completed this week with handover to follow

Freight Store – 4 of 6 new columns installed, 5th to follow by the end of this week

Freight Office – Vinyl flooring to be completed this week with handover to follow

Balcony – Steelwork installation has commenced and is due to be completed by the end of the weekend.

Chiller – Concrete pour of slab complete. Cold store ducting and doors in progress followed by commissioning.

Parting Carn:

Batching concrete for quay extension and freight store foundations

Receipt of Quay Widening blocks.

Porthloo:

Bag filling for delivery to Parting Carn or direct to the quay continues.

The second phase or final removal remains on target weather permitting for mid October 2015.

Kier has installed cameras on all working vehicles with a recording facility for appraisals and record

purposes.