St Mary’s Quay Works Update From Kier 18th September

St Mary’s Harbour Improvement Project Weekly Update :
Week Ending 18 September 2015

Quay Extension:

Anchors to be grouted, grout due week ending 18 Sep 15.

Crane transfer off the jack-up barge completed.

Jack up barge demobilisation and exit anticipated end of this week.

Quay Widening:

Package Pump Station – delivery expected end of next week from Falmouth.

Installation process anticipated to commence 28-30 Sep 15 and last 10-14 days.

Delivery of precast units has now reached 80%.

Harbourside building:

Ticket Office – Vinyl flooring to complete end of this week

Freight Store – Excavation & casting end of this week. 2 columns remaining.

Freight Office – Flooring to complete end of this week with possible handover next week.

Balcony – Excavation of foundations by this week end with casting next week. Duration 5-7 days.

Commemorative blocks installed on the North Gable End of the Harbourside.

Chiller – Delivered. Concrete pour of slab end of this week. Cold store ducting and doors next week

followed by commissioning.

Parting Carn:

Batching concrete for Freight Store foundations and cold room slab.

Receipt of Quay Widening blocks.


Bag filling for delivery to Parting Carn or direct to the quay continues.

The second phase or final removal remains on target weather permitting for mid October 2015.