St Mary’s Harbour Improvement Project Weekly Update

St Mary’s Harbour Improvement Project Weekly Update

Week Ending 11 September 2015

-Quay Extension

Crane transfer off the jack-up barge in progress this week.

-Quay Widening

Package Pump Station under fabrication off site.

Delivery of precast units continues from Falmouth.

Mobilising of solidification plant – due on site week commencing 14 Sep 15.

-Harbourside building

Ticket Office – Vinyl flooring and 2nd fix electrical works ongoing.

Freight Store – 1st bay of new column and lintel beam installed. 2nd bay ongoing.

Freight Office – Finishing works continue.

Balcony – Steelwork arrived, erection to commence next week

Final Commemorative block to be removed this week followed by installation of all blocks to the North

Gable End of the Harbourside also this week.

Chiller – Cold room installation this week.

-Parting Carn

Batching concrete for Freight Store foundations and cold room slab.

Receipt of Quay Widening blocks.

-Porthloo

Bag filling for delivery to Parting Carn or direct to the quay continues.

The second phase or final removal remains on target weather permitting for mid October 2015.