St Mary’s Harbour Improvement Project Weekly Update

Week Ending 04 September 2015:

 

Quay Extension

  • Tensioning of the anchors and grouting continues with shutter assembly and preparation for tie-in concrete pour.
  • Crane transfer off the jack-up barge now expected end of this week.

 

Quay Widening

  • MMO for solidification option now approved and received, mobilisation underway.
  • Package Pump under fabrication.
  • Boulder field clearance and ramp construction complete.
  • First delivery of precast units has arrived from Falmouth.

 

Harbourside Building

  • Ticket Office – Vinyl flooring and 2nd fix electrical works pending.
  • Freight Store – First section of steelwork complete.
  • Freight Office – Finishing works continue.
  • Balcony – Steelwork delivery week commencing 07 Sep, erection week commencing 14 Sep.
  • Removal of Commemorative blocks, two removed and one remaining – to be relocated to the North
  • Gable End of the Harbourside building.

 

Parting Carn

  • Batching concrete for Freight Store foundations and material storage.

 

Porthloo

  • Bag filling for delivery to Parting Carn or direct to the quay continues.
  • The second phase or final removal remains on target weather permitting for mid October 2015.