Kier Construction St Mary’s Harbour Works Update

St Mary’s Harbour Improvement Project Weekly Update

Week Ending 21 August 2015

Quay Extension

The last set of blocks; L10 and L11 have now been installed.

above. Grouting to control billets on-going, survey to tie-in.

Quay Widening

Breakthrough of the quay wall now complete, additional work for the tie-in on-going construction of the

ramp and some boulder field clearance remains but a breakwater using the boulders is complete.

Stop log columns now installed.

Harbourside building

Ticket Office roller shutter doors – Fitting has commenced, expected to complete by Friday 21 Aug

New Chiller Store Structural Steelwork erection complete.

Freight Store – Temporary works continue.

Freight Office – Finalising second fix electrics (light fittings, etc.) and plumbing

Balcony – Breaking out to form concrete plinth for tie-in connection detail complete. Steelwork to

commence early September.

Removal of Commemorative blocks now on-going – to be relocated to the North Gable End of the

Harbourside building.

Parting Carn

Phase one of the re use of material stored at Parting Carn is now complete and pending delivery to

the quayside with more to follow.