Kier Construction St Mary’s Harbour Works: Week Ending 14 August 2015

Quay Extension:

Both stone and block barge with blocks L10 and L11 in Falmouth awaiting an appropriate weather

window.

Aggregate fill of levels 7, 8 and 9 now complete.

Grouting to control billets on-going, survey to tie-in.

Quay Widening:

Breakthrough of the quay wall, construction of the ramp and clearance of the boulder field continues.

2nd Stop log column has been cast. Stop Logs now on site.

Harbourside building:

Ticket Office roller shutter doors to be fitted week commencing 17 Aug 15.

New Chiller Store Structural Steelwork erection to start week commencing17 Aug 15.

Waiting Room – Handed over Friday 07 Aug 15.

Freight Store – Temporary works being installed.

Freight Office –With second fix electrics (light fittings, etc.) and plumbing in progress

Balcony – Breaking out to form concrete plinth for tie-in connection detail. Steelwork to follow.

Removal of Commemorative blocks has started – they will be relocated to the North Gable End of the

Harbourside building:

Parting Carn

Phase one of the re use of material stored at Parting Carn is now complete and pending delivery to

the quayside.

Porthloo:

Phase two of operations to re-use the material at Porthloo for the Quay Widening has been re-

planned and will now commence this week.