St Mary’s Harbour Improvement Project Weekly Update From Kier

Week Ending 24 July 2015:

Quay Extension:

Aggregate fill of Level 6 is nearing completion as shown above.

Level 7 blocks will commence this week weather permitting when

construction will be clearly visible above sea level.

Quay Widening:

Clearing of the boulder field will commence shortly in preparation for construction of the ramp.

Harbourside building:

Waterproofing of the Ticket Office is 90% complete, pending balcony & balustrade finishing’s.

Windows now fitted with rendering this week.

Recently instructed New Chiller Store Structural Steelwork currently under fabrication. Erection to

commence week commencing17 Aug 15.

Waiting Room – Painting continues with flooring & furniture scheduled for next week.

Staircase & Balcony steelwork in fabrication expected this week.

Freight Store has been suspended to 01 Sep 15. Freight Office – Door linings and rendering in progress followed by M & E.

Parting Carn – Recycling:

A Crusher will be installed to separate concrete, construction & waste material.

Bicycles have now been received and utilised by Kier staff reducing the use of fossil fuel transport

and subsequently the carbon footprint.


Daily maintenance of the material at Porthloo will continue.

Precast yard in Plymouth – Final Casting Phase

Quay Extension – 12 Slabs & 6 Infill blocks complete

4 flights of stairs complete by end Jul 15.

Quay Widening blocks and remaining13 Parapet Wall Units now complete.