KIer Construction St Mary’s Harbour Update

Kier has been delayed in sending out their weekly update. Although it says July 10th, this is what was distributed today, Tuesday the 14th.

St Mary’s Harbour Improvement Project Weekly Update 10 July 2015

Quay Extension

Level 5 is now complete with the 6th level progressing.

Harbourside building

The Ticket Office roof installation continues with roof finishing’s following on.

New Chiller Store Structural Steelwork currently under fabrication. Erection shall commence 15 Aug 2015.

Waiting Room Door and window delivery scheduled for 11 July 2015 with flooring to follow.
Balcony site survey complete, steelwork currently in fabrication.

Freight Store has been suspended to 01 Sep 15.

Freight Office works continue, hard boarding of walls and ceilings with plastering following on.

Parting Carn – Recycling

A Crusher will be installed to separate CDW, construction, excavated & demolition waste/material.

Porthloo
Daily maintenance of the material at Porthloo will continue.
Re-use of material has now been accepted by the MMO for use in the Quay widening area.

Precast yard in Plymouth
Quay Extension Blocks and casting phase of 12 Slabs 100% complete

6 Infill blocks and 4 flights of stairs will complete by 18 Jul 15.

Quay Widening blocks complete with remaining13 Parapet Wall Units currently under construction.