St Mary’s Harbour Improvement Project Weekly Update 03 July 2015

Quay Extension:

The 4th layer of 18 blocks has arrived and installation will commence shortly weather permitting.

Harbourside building:

Waiting room installation of windows & doors pending delivery on 09 July 15.

The Ticket Office wall cladding and roof is in progress.

New chiller store main Slab pour complete. Roller Shutter doors, external door and window will be

installed after delivery on 09 July 2015. Internal fit out and M & E will commence on 13 July 2015.

Waiting Room Door and window installation scheduled for 09 July 2015. M & E expected to start 13th

July 2015. Flooring scheduled for 20 July 2015 with skirting, chairs and handrails to follow

approximately 4 days later.

Balcony site survey complete, steelwork delivery anticipated in four weeks.

Freight Area & Store temporary works suspended to 01 Sep 15.

Freight Office pending delivery of window and door 09 July 2015, block work complete, internal fit out

continuing.

Parting Carn:

A Crusher will be installed to separate all CDW, construction, excavated & demolition waste/material

for recycling.

Porthloo:

Daily maintenance of the material at Porthloo will continue.

Re-use of the material remains pending approvals.

Precast yard in Plymouth:

The next casting phase of 12 Slabs, 6 Infill blocks and 4 flights of stairs will complete by 10 Jul 15.

Quay Extension block casting is at 100%.

Quay Widening block casting is at 100%.